Refer to RUS Bulletin 1767B-3, Preparation and Use of the RUS Form 254, for instruction in accounting for all contract costs, including the retirement of units removed by the Contractor and the unitization by record units of costs of construction assemblies installed by the contractor.
The instructions for submitting and distributing this form (if required) are included in 7 CFR 1726, Electric System Construction Policies and Procedures.
Field Name/ |
Instruction |
Sheet |
Enter the sheet number and total number of sheets submitted. |
Date |
Enter the Project date. |
Project Designation |
Enter the Project designation. |
Contract No. |
Enter the Contract number. |
Borrower |
Enter the Borrower’s name. |
Engineer |
Enter the Engineer’s name. |
Contractor |
Enter the Contractor’ name. |
RUS Project Codes |
Enter RUS project codes. |
A |
Enter the total cost of standard, new and conversion assembly units installed. |
B |
Enter the cost to remove “I” units. |
C |
Enter the amount to be credited to contractor for materials removed from existing facilities and returned. |
D |
Enter the amount chargeable to contractor for materials in assembly units. |
E |
Enter the net amount of owner-furnished materials. |
F |
Enter the net amount due to contractor. |
Certification of Engineer |
Enter the new amount due to contractor. Enter the contractor’s name. Enter the date signed. Signature line. |
Acceptance by Owner |
Enter the owner’s name. Enter the date signed. Signature line. |
Acceptance by Contractor |
Enter firm’s name. Enter date signed. Signature line. |
Refer to RUS Bulletin 1767B-3, Preparation and Use of the RUS Form 254, for instruction in accounting for all contract costs, including the retirement of units removed by the Contractor and the unitization by record units of costs of construction assemblies installed by the contractor.
The instructions for submitting and distributing this form (if required) are included in 7 CFR 1726, Electric System Construction Policies and Procedures.
Field Name/ |
Instruction |
Sheet |
Enter the sheet number and total number of sheets submitted. |
Date |
Enter the Project date. |
Project Designation |
Enter the Project designation. |
Contract No. |
Enter the Contract number. |
Engineer |
Enter the Engineer’s name. |
Contractor |
Enter the Contractor’s name. |
Quantity /1 |
Enter the quantity of assembly units. |
Unit NO./Type /2 |
Enter the unit number and type of assembly units. |
Labor Unit Price/ 3 |
Enter the labor unit price due contractor for units installed, converted, and removed. |
Material Unit Price/ 4 |
Enter the material unit price due to contractor for units installed, converted, and removed. |
Total Unit Price/ 5 |
Enter the total unit price due to contractor for units installed, converted, and removed. |
Cost of Construction/6 |
Enter cost of construction due to contractor for units installed, converted, and removed. |
Cost to Remove “I” Units/ 7 |
Enter the cost to remove “I” units due to contractor for units installed, converted, and removed. |
Unit Value/ 8 |
Enter the unit value of amount chargeable to Contractor for materials in assemblies removed. |
Total /9 |
Enter total of all applicable columns. |
Total |
Insert Total of All Applicable Columns. |
Refer to RUS Bulletin 1767B-3, Preparation and Use of the RUS Form 254, for instruction in accounting for all contract costs, including the retirement of units removed by the Contractor and the unitization by record units of costs of construction assemblies installed by the contractor.
The instructions for submitting and distributing this form (if required) are included in 7 CFR 1726, Electric System Construction Policies and Procedures.
Field Name/ |
Instruction |
Sheet |
Enter the sheet number and total number of sheets submitted. |
Date |
Enter the Project date. |
Project Designation |
Enter the Project designation. |
Contract No. |
Enter the Contract number. |
Engineer |
Enter the Engineer’s name. |
Contractor |
Enter the Contractor’s name. |
Item Designation 10 |
Enter the item designation of amounts to be credited to contractor for materials returned. |
Description of Material/-11 |
Enter the description of material amounts to be credited to contractor for materials returned. |
Quantity/ 12 |
Enter the quantity of amounts to be credited to contractor for materials returned. |
Item Value Table D In Contract/ 13 |
Enter the item value in contract of amounts to be credited to contractor for materials returned. |
Total Credit To Contractor/14 |
Enter the total credit to contractor for amounts to be credited to contractor for materials returned. |
Quantity/15 |
Enter the quantity of items of returned materials declared reusable by engineer. |
Stock Card Item Price/16 |
Enter the stock card item price of returned materials declared reusable by engineer. |
Salvage Value /17 |
Enter the salvage value of returned materials declared reusable by engineer. |
Total |
Insert Total of All Applicable Columns. |
Refer to RUS Bulletin 1767B-3, Preparation and Use of the RUS Form 254, for instruction in accounting for all contract costs, including the retirement of units removed by the Contractor and the unitization by record units of costs of construction assemblies installed by the contractor.
The instructions for submitting and distributing this form (if required) are included in 7 CFR 1726, Electric System Construction Policies and Procedures.
Field Name/ |
Instruction |
Sheet |
Enter the sheet number and total number of sheets submitted. |
Date |
Enter the Project date. |
Project Designation |
Enter the Project designation. |
Contract No. |
Enter the Contract number. |
Engineer |
Enter the Engineer’s name. |
Contractor |
Enter the Contractor’s name. |
Item Designation/ 18 |
Enter the designation for tabulation of net amount of materials furnished by Owner. |
Description of Material/ 19 |
Enter the description of material for tabulation of net amount of materials furnished by Owner. |
Quantity/20 |
Enter the quantity for tabulation of net amount of materials furnished by Owner. |
Unit Cost/21 |
Enter the unit cost of actual cost to the Owner. |
Extended Cost/22 |
Enter the extended cost of actual cost to Owner. |
Unit Price/23 |
Enter the unit price of amount chargeable to Contractor at contract price. |
Extended Cost/24 |
Enter the extended cost of amount chargeable to Contractor at contract price. |
Excess of /25 |
Enter the extended cost of amount chargeable to Contractor at contract price over extended cost of actual cost to Owner. |
Total |